Vale Inco - Goro Nickel Project, New Caledonia |
|
Return to Project List
- Conducted an audit of the Project HS&E Plans and Procedures to determine gaps in requirements
- Developed comprehensive Hazardous Energy Control (HEC) and General Work Permit (GWP) procedures and associated permits to allow site commission of High Voltage installations
- Identified process and development plan to close gaps to meet requirements of Project HS&E Plans
- Developed comprehensive auditing documents for Goro Nickel Projects health and Safety Procedures and instructions
- Developed an excel database used to capture and report on audit findings
- Developed database to be able to:
- report on Individual, Manager, Area and Contract group compliance to audit schedule
- report on audit compliance score with ability to drill down to individual audit point compliance
- report daily, weekly, monthly, yearly, year to date and over a specified time frame
- Prepared a Commissioning Induction based on LOTO/Permit to Work and Commissioning Execution Plan
- Delivered the induction to current Commissioning staff
- Assisted with updating Site induction to include Commissioning elements
- Assessed current application of JSA process within Commissioning team
- Undertake an analysis of the training needs for Goro Nickel Project Construction and Commissioning personnel
- Identified specific competency standards required from training delivery
- Developed role specific training plans
- Identified training provision options
- Coordinated delivery of training
- Audited effectiveness and implement improvements as required
- Targeted recruitment for specialist roles:
- Commissioning Safety Manager
- Commissioning Engineers
- Safety Professionals
- Isolation and Permitting Officers
- Risk Assessment Facilitators
- Trainers
|