BHP Billiton – Olympic Dam, SA

Return to Project List

  • Developed the following:
    • Mechanical, Electrical & Instrumentation Work Instructions
    • Standard Operating Procedures
    • Training competencies
    • Confined Space Register
  • Fine tuned all isolations, Permit to Work, confined space, hot work permit, etc documentation
  • Defined permit huts, lock boxes, locks, critical isolation material
  • Created special case registers (i.e. whereby positive isolation can not be achieved)
  • Created Permit to Work and isolation management procedures
  • Created training material (i.e. Presentations, Authorisation forms, scripts for filming)
  • Reviewed & added relevant information in engineering specifications to meet the intent of FRCP 8
  • Facilitation of key stakeholders in the development of a Safety Management plan for major maintenance shutdowns within the Mine Fixed plant and Infrastructure area
  • Developed THA's and Work Instructions for the maintenance Planning Department
  • Created Safety and Technical information manuals for the electrical department
  • Developed Maintenance Work Instructions for the new Scats Vibrating Screen Facility
  • Provided advice and assistance to the Smelter Department personnel with the implementation and coordination of the Permit to Work, Energy Control and other safety system requirements
  • Developed work instructions and other documents associated with the RCM implementation project
  • Assisted the Concentrator Hydromet area to develop Task Hazard Analysis (THA) documents required for the Dual Mill Shutdown
  • Provided advice and assistance to Concentrator Hydromet Department personnel with the implementation and coordination of the Permit to Work, Energy Control and other safety system requirements
  • Edited and developed HSEC documentation
  • Provided Permit to Work and Isolation Training Facilitation
  • Provide Permit Acceptor Training
  • Provided consultant for the implementation of the FRCS 3.8 Confined Space Management System